Transmission - K-Electric

Transmission

Merit Order Sheet


The transmission system of KE comprises of 1354km of 220kV, 132kV and 66kV lines, with 71 grid stations, 20 auto transformers and 181 power transformers.
 

transmission network data

With a vision to supply uninterrupted electricity and to bridge the gap between valued customers and K-Electric, a significant investment is made in recent years. Major initiatives were taken in areas of Capacity Enhancement, Grid station and Transmission line augmentation and rehabilitation.

Transmission System Enhancement

Owing to the investment made in transmission system, the MVA capacity increased by around 3000 MVA and the overall transmission losses improved by 3.17% points since the start of FY09.

MVA transmission network timeline
Loss transmission network timeline

Following grid stations have been added in the system

transmission network full timeline

List of Transformers installed in the system post July’ 2018:

40 MVA

Hub Chowki

October 2018

40 MVA

Surjani

October 2018

40 MVA

Valika

November 2018

40 MVA

Elander Road

December 2018

40 MVA

Shadman

December 2018

40 MVA

Mauripur

January 2019

40 MVA

Shadman

January 2019

40 MVA

Old Town

January 2019

40 MVA

KEPZ

January 2019

40 MVA

Malir

January 2019

40 MVA

Port Qasim

February 2019

40 MVA

PRL

March 2019

40 MVA

Old Golimar

March 2019

40 MVA

Old Golimar

March 2019

40 MVA

Qayyumabad

April 2019

40 MVA

Queens Road

April 2019

40 MVA

Valika

April 2019

40 MVA

KDA

June 2019

40 MVA

Baldia

July 2019

40 MVA

Creek City

August 2019

10 MVA

Gadap

October 2019

40 MVA

Creek City

November 2019

40 MVA

Labour Square

November 2019

40 MVA

Labour Square

November 2019

40 MVA

Pipri West

December 2019

40 MVA

DHA-1

December 2019

40 MVA

AKUH

December 2019

40 MVA

Queens Road

February 2020

40 MVA

Federal-B

February 2020

40 MVA

Defence

February 2020

40 MVA

BOC

February 2020

40 MVA

Garden East

March 2020

40 MVA

Hub Chowki

July 2020

39 MVA

KDA

September 2020

40 MVA

Maymar

January 2021

40 MVA

Mehmoodabad

March 2021

40 MVA

Mehmoodabad

March 2021

30 MVA

Pipri West

July 2021

40 MVA

PRL

August 2021

40 MVA

Korangi South

September 2021

40 MVA

Landhi

November 2021

40 MVA

Memon Goth

November 2021

40 MVA

Gulshan-e-Maymar

December 2021

40 MVA

Landhi

April 2022

40 MVA

Agha Khan

July 2022

40 MVA

Landhi

December 2022

Continuing with its mission of keeping Karachi illuminated, by far in FY23 KE has enhanced its transmission capacity by 100MVA with addition of new power transformer at Agha Khan grid and Landhi grid, alongside enhancement in existing grids taking total transformation capacity to 6,903MVA. A new 132kV Site – Haroonabad circuit – II is also energized increasing the reliability of the system. Furthermore, projects including reconductoring of transmission lines and RTV coating of insulators are in progress that aim to improve system reliability.

Initiatives

To manage the growing power demand of the metropolis while ensuring optimal utilization of transmission infrastructure and reliability in power supply, KE has developed long term transmission expansion plan till FY30.

Furthermore, considering the surplus capacity scenario in the National Grid, KE is in the process of setting up of new grids and interconnection works which would enable drawl of additional power from the National Grid in addition to 1,100 MW currently being evacuated. In this regard, the process for setting up of new grid at 500kV level is in progress. Whereas the construction of new 220 kV Dhabeji Interconnection is in full swing. Upon completion of these grids and interconnection works, KE will be able to import additional power from the National Grid which will enable KE to manage the demand in upcoming years alongside enhancing system reliability.

In addition to above, as per KE’s plan to bring a substantial change in the rural parts of its service territory by upgrading its infrastructure in these areas to meet the increasing load profile and to help economic expansion, KE is carrying out large-scale rehabilitation project of existing 132kV and 66 kV transmission lines in Hub, Vinder, Uthal and Bela regions on an accelerated pace. Phase-I of the project is at the verge of completion with 98.25%, whereas Phase-II stands at 93.15%, and both the phases are expected to be completed by the end of FY23.

Moreover, under flagship project of 900MW BQPS-III, upgradation of transmission network is planned that includes augmentation of two critical load grids and two generation interconnection grid stations. One load grid (New Landhi) has been energized which will not only improve reliability of the network but will also help catering new industrial load growth. Also, the new interconnection at KTPS will evacuate power of KPC on 132kV system rather than on 220kV viz-a-viz corelating embedded generation and improving the network efficiency.

Your Opinion Matters!

We're making important changes to our website. Your input is crucial. Please take a moment to share your thoughts.



No thanks

Powered by K-Electric

This will close in 0 seconds

WordPress Lightbox